Q. CPM is the

A
Event oriented technique
B
Target oriented technique
C
Activity oriented technique
D
Time oriented technique
Solution:
  • The Critical Path Method (CPM) is a project management technique used to schedule and manage complex projects consisting of a series of interdependent activities.
  • It focuses on identifying the critical path, which is the longest sequence of dependent tasks that determines the minimum time required to complete the project.
  • The first step in CPM is to identify all the activities required to complete the project. Each activity should have a defined start and end point.