Q. The process of reducing activity time by adding resources resulting in the increase of cost is called:

A
Reducing
B
Updating
C
Optimizing
D
Crashing
Solution:

Crashing is the technique to use when fast tracking has not saved enough time on the schedule. It is a technique in which resources are added to the project for the least cost possible.Crashing is another schedule compression technique where you add extra resources to the project to compress the schedule.