Q. The amount of time by which an activity can be delayed without increasing the completion time of a project is known as

A
Float
B
Stack
C
Dummy
D
All of the above
Solution:

Slack and Float refer the same meaning, But
In CPM an activity oriented technique it is called Float.

PERT an event oriented technique it is called Slack.