Q. The difference between the latest allowable time and the earliest expected time is

A
Maximum float
B
Total float
C
Slack time
D
Free float
Solution:

Slack time

It denotes the amount of time each activity can be delayed without violating the entire project duration. The slack of an activity can be calculated as the difference between its latest start and earliest start time, or alternatively, as the difference between its latest and earliest finishing time.