Q. The difference between the latest allowable time and the earliest expected time is
Solution:
Slack time
It denotes the amount of time each activity can be delayed without violating the entire project duration. The slack of an activity can be calculated as the difference between its latest start and earliest start time, or alternatively, as the difference between its latest and earliest finishing time.