Q. Minimum period before striking formwork to slabs

A
21 days
B
7 days
C
3 days
D
1 day
Solution:
  • The process of removal of formwork or shuttering in the process of casting concrete is known as striking.
  • Minimum period before striking formwork to slabs is 3 days.